Framing Day 1
they were here right at 530am. to protect my new concrete floor they put over 100 sheets of OSB down to cover it. they almost built one 70' wall entirely and laid out the other long wall.
they ordered the trusses off of the actual wall measurements today and they will be here mid next week. they will likely have the 4 walls framed out by wednesday. then crane day comes where they assemble it like a gigantic wood erector set.
this last week it finally feels real.
tom
they were here right at 530am. to protect my new concrete floor they put over 100 sheets of OSB down to cover it. they almost built one 70' wall entirely and laid out the other long wall.
they ordered the trusses off of the actual wall measurements today and they will be here mid next week. they will likely have the 4 walls framed out by wednesday. then crane day comes where they assemble it like a gigantic wood erector set.
this last week it finally feels real.
tom