no. there is a rough plumbing inspection first, and then they come out and wrap the plumbing prior to concrete. i think they are also going to have to hand dig out the footings since the rain made the fill up with mud. ....that said, i hope to have a slab next week.
the builder says he hopes to have it all framed up in 7-10 days. so, hopefully the framed structure will be up by the end of august.
tom
2002 45'8" Newell Coach 608 Series 60 DDEC4/Allison World 6 Speed HD4000MH
Posts: 296
Threads: 21
Joined: Mar 2014
It will be exciting to see walls going up, it will put the size in perspective.
Love old school
1976 Newell 8.3 cummins allison 6spd
1977 Newell 8.3 cummins allison 6spd
Posts: 4,188
Threads: 635
Joined: Jul 2012
It will be interesting to see the neighbors reaction to your highrise garage!!
Michael Day
1992 Newell 43.5' #281
NewellOwner.com
Posts: 5,751
Threads: 493
Joined: Jul 2012
i have told those that i have met about it and that it will be TALL. it will be a really nice looking building so i doubt anyone will think ill.
tom
2002 45'8" Newell Coach 608 Series 60 DDEC4/Allison World 6 Speed HD4000MH
Posts: 5,751
Threads: 493
Joined: Jul 2012
Posts: 4,188
Threads: 635
Joined: Jul 2012
Hopefully the weather will stay dry until after the forming is complete and the slab is poured and at least partially cured.
Michael Day
1992 Newell 43.5' #281
NewellOwner.com
Posts: 5,751
Threads: 493
Joined: Jul 2012
Posts: 5,751
Threads: 493
Joined: Jul 2012
Posts: 296
Threads: 21
Joined: Mar 2014
Hopefully the rain stays away till after the pour, would hate to see it all wash in again.
Love old school
1976 Newell 8.3 cummins allison 6spd
1977 Newell 8.3 cummins allison 6spd
Posts: 1,532
Threads: 155
Joined: Jul 2012
Tom,
Im loving these posts! That is gonna be HUGE! besides the coach, what are you gonna fill it up with?