Posts: 4
Threads: 0
Joined: Jul 2019
Tested it tonight . Both relays are connected and passing 120V to compressors. It feels colder inside but it was over a 100 most of today just East of Dallas. I will let it run tonight, and then button up the relay circuit box and mount it in place. Thank you for all your help. #NewellGurus are amazing. Please ping me with questions. The last diagram (compact version) is what I used. I did have to swap the A1 / A2 on one relay to make the connector trigger. That wire pair may have been reversed since that is the one that melted the plug —the reason for the relays —and is now just 2 wires soldered to the circuit board in place of the melted plug, and melted wires.
1996 Holiday Rambler Navigator
Diesel Pusher / Onan 10Kw Generator
No Tow Vehicle
Pontoon Boat at the Lake
Posts: 5,409
Threads: 255
Joined: Jul 2012
You probably did, but just to make sure. Comp 1 runs on one hour leg(black) and comp2 runs on the other (red) to keep the loads balanced. If you have four units, then reverse the legs for
The second unit to keep the loads balanced
Glad you are cool now!
Richard and Rhonda Entrekin
99 Newell, 512
Maverick Hybrid Toad
Inverness, FL (when we're home
)
Posts: 314
Threads: 7
Joined: Mar 2020
I just completed this mod today. Thanks to Chester for the pictures and Richard for the dummy resistant theory of installation of the mod. I also made sure the upper and lower circuits on each side did not use the same hot leg so the loads will be more balanced.
I was able to source contactors locally for $22 each. MCG Industrial PN: MDP30A-2P-120
https://drive.google.com/file/d/1ICqJfXb...sp=sharing
These contactors have two circuits but I only used one side of the contactor. They also need a pretty tall enclosure vs. the short box I saw on Richard's coach. It is more expensive and water proof but the supply house had it on the shelf and I was able to mock up the inside of the box while in the store.
https://drive.google.com/file/d/1RQcZ0Xj...sp=sharing
The first side took me about 3 hours to complete. I took my time and checked things 3 times over before I snipped any wires.
The second time (1 week apart as I was awaiting parts) took me 2 hours to complete. Again I was working slow and methodical. The penalty for screwing up far exceeded the reward for finishing an hour early.
Thanks again to Chester, Richard and all those who added to this thread. Each entry was important to help me understand this.
Hank & Natalie Bensley
2001 Double Slide #586.
2021 Cherokee Trailhawk Toad
Port Orange, FL. Upcoming Snowbirds in Endwell, NY
(This post was last modified: 05-15-2021, 10:00 AM by
hbens.
Edit Reason: added link to enclosure
)
Posts: 5,751
Threads: 493
Joined: Jul 2012
Posts: 26
Threads: 2
Joined: Aug 2021
Tom, led lights are a very nice touch. Power check at a glance.
Posts: 5,409
Threads: 255
Joined: Jul 2012
That was @"bikestuff" addition to the modification. It’s on my “list”to go back and add them.
Richard and Rhonda Entrekin
99 Newell, 512
Maverick Hybrid Toad
Inverness, FL (when we're home
)
Posts: 5,751
Threads: 493
Joined: Jul 2012
bill is a genius, so is richard
tom
2002 45'8" Newell Coach 608 Series 60 DDEC4/Allison World 6 Speed HD4000MH